Project Background

Capital Water Systems were employed by Galway City Council to carry out monitoring and sampling at three separate beach and outfall locations in the Ballybane/Renmore/Mervue area of Galway.

The aim of the project was to determine to what extent, if any, the outfalls were contributing to Bathing Water quality issues at Ballyloughaun Beach.

Beach Monitoring Contract 1

Project Requirements & Tasks

N

13 Week flow and rainfall survey at three outfall locations

N

Weekend sampling program for microbial and chemical sampling at 3 beach and three outfall locations

N

Constant contact with client in relation to microbial results

N

Installation of additional CSO monitors in each catchment

N

Weekly calibration checks & interim reporting

N

Office support as required

N

Final report to client

Solutions Delivered To Client

  • Consistent accurate flow data from all flow and CSO monitoring sites
  • Consistent sample capture
  • Identification of possible problem CSO with very low threshold spill activation
  • Confirmation of rainfall intensity rates for CSO activation
  • Confirmation that remedial work on CSO did not back site flows downstream